Yarn-to-Needle Process Improvement and Order Release Scheduling

Date
2012-12-12Author
Broadley, Sarah
Durán, Gilda Maria Carbo
Chen, Hongfan
Mordel, Eran
Villarreal, Adrian
Zeman, Kyle P.
Metadata
Show full item recordAbstract
Interface, Inc.,
is the world’s largest modular carpet manufacturer. Their facility in West
Point, GA. has experienced lost demand due to lack of capacity, overtime expenses, constrained space, and delayed orders. Our team delivered process improvement and
capacity expansion recommendations based on a simulation, and an order
scheduling decision-support tool. Interface can expect approximately 20% increase in capacity, $2 million in annual savings, and up to 85%
reduction in delayed orders.